Our solution
MEGA started the implementation work in January 2023. First, the remediation work was carried out (removal of ruderal growth, infestations and unproductive trees), and the selected trees underwent professional arboricultural treatment. Subsequently, deciduous avenue and fruit trees of both original and new resistant varieties (lime, apple, pear, plum and cherry) were planted, a lawn was established, and urban furniture was installed.
Within the project, a total of 46 trees were felled, 19 original trees were treated, 50 new trees were planted and 4,500 m2 of lawn was established. The area was also equipped with furniture in the form of benches, a picnic set, a tourist information board, a bin and a directional signpost. The completed work was then handed over to the client in May 2024 without any defects or shortcomings.